Novel material with unique metallurgy and more than 60 HRC hardness which leads to increased life has been suggested for this in-situ reconditioning of coal mill tyre in major power plant industry
2 Mills are successfully completed and consumption of materials and each mill approximately consumed 500 kg and 150 kg for different layers.
Further, completion time for one mill is around 3-4 days for reconditioning using X’tralife tailor made products having chromium carbides with columnar dendrites
Overall, this thereby reduces the downtime losses and operational costs resulting into absolute improvement of the bottom line for the organization. Hence, this giant power industry is in talks to give us order of 10 mills for rebuilding in accordance with coal mill tyre.