OVERVIEW OF PLANT :
Stage 1: 660 MW
Stage 2: 660 MW
Stage 3: 1320 MW
Stage 4: 1980 MW
PRODUCT :
COAL MILL CAPACITY : 70 TPH
NO . OF MILL : 52 MILLS
CONSUMPTION :
2 Mills are successfully completed and consumption of materials are as follows :
Each mill approx consumption
Further, completion time for one mill is around 3-4 days.